Cookie Notice

This site does not use tracking cookies of any sort. It does store a Session Cookie. This is a security cookie and ensures that if the administrator of the site forgets to log out of the site, after 10 minutes of inactivity, the site will automatically time out. This cookie is automatically deleted at the end of the every session and contains no personal information. We do not use these cookies for any purpose other than as stated above. For further information please click here.

To reset your cookie permissions please click the reset link at the bottom of this page.


Get me out of here...

Welcome to the Kilbeggan to Mullingar Greenway Project

The Project

Westmeath County Council in conjunction with Transport Infrastructure Ireland (TII) intends to deliver a greenway from Kilbeggan to Mullingar. This section of greenway will complete a strategic link between the established greenway infrastructure on the Grand Canal Greenway (linking Kilbeggan with Tullamore) and the Old Rail Trail/ Royal Canal Greenways (linking Mullingar with Athlone, Dublin, and Longford). This will provide a high-quality greenway, designed to promote cycling, walking and other non-motorised travel.

In 2023, WCC appointed Tetra Tech | RPS to deliver the Kilbeggan to Mullingar Greenway Project through Phases 1 to 4 of the TII Project Management Guidelines.

Progress to Date

In Phase 1 (Concept and Feasibility), the first non-statutory public consultation for the Kilbeggan to Mullingar Greenway Project was held in May 2023 and displayed the study area for the project. Feedback from the first public consultation helped inform the identification of areas of interest and constraints, which in turn informed the development of route corridor options within which a route for the greenway could be developed.

In Phase 2 (Options Selection), two feasible route corridor options were identified to connect tourism and leisure attractions and use publicly owned land where possible. Both route corridor options start in Kilbeggan Harbour and end in Mullingar with one corridor to the west of Lough Ennell and one corridor to the east of Lough Ennell.

A second public consultation was held in May 2024 where the two route corridor options were displayed. Feedback from the second public consultation helped inform the appraisal process of the route corridor options. Other factors that were considered in the appraisal included the project objectives, the locations of attractions within the corridors, and environmental constraints.

Following the completion of the Options Selection appraisal for the Kilbeggan to Mullingar Greenway a third public consultation was held from 16th June through 25th July 2025 to update all stakeholders, landowners, members of the public and interested parties on project progress. The Emerging Preferred Route Corridor (EPRC) which was developed matching the best performing segments of the two route corridor options was displayed.

Submissions and feedback received during Public Consultation No.3 were collated and assessed as part of the process to select the Preferred Option corridor which is available to view below.

The area represented by the Preferred Option corridor does not represent the extent of lands required for the provision of the project; instead, it indicates the lands within which the project could be feasibly developed.

What's Happening Now

The Preferred Option corridor map is now available to view below. It is also published along with the Options Selection Report on the ‘Downloads’ tab. The next phase of TII’s planning and design process, Phase 3 – Design and Environmental Evaluation has now commenced. In this Phase, work will commence on identifying a route within the Preferred Option corridor.  This involves developing the project design based on both technical and environmental inputs, to a stage where sufficient levels of detail exist to establish landtake requirements, to identify and mitigate project impacts, and to progress the project through the statutory processes.

Throughout the Phase 3 process, the Project Team is committed to continuously engaging with people living, working or who own land and property within the Preferred Option corridor, however the design of the greenway and identification of the impacts on land and property will take some time to develop. 

In order to inform the design process, the Project Team will first undertake a range of engineering and environmental site surveys. The design team will be in contact with relevant landowners to arrange these surveys.

As the site surveys are completed, the preliminary design and environmental evaluation of the greenway can be progressed. When the design has reached a level of maturity where informed discussions can take place, the Project Team will consult with directly impacted landowners in relation to the initial design and its impact on land and property. Thereafter, feedback will be considered, and amendments may be made, where feasible, before finalising the design.

Preferred Option Corridor

The Emerging Preferred Route Corridor EPRC has been refined with consideration to submissions and feedback received during the consultation period, along with maximising the use of state-owned lands and removing areas from the EPRC where it was considered unlikely that a route would be developed, thereby assisting the Project Team in finalising the Preferred Option corridor.

The Preferred Option corridor is available to view in the interactive map linked below. Stakeholders can use this map to search Eircode’s and see their locations relative to the Preferred Option corridor. There is also a zoom function available which can be used to provide a more detailed overview of the Preferred Option corridor at specific locations.

The Preferred Option corridor map is also available to download or print below.

back to top